Overseas power plants
Australia
• Generated and distributed electric power totaled 1,950,925 megawatts-hour
RATCH has an indirect holding in the Thang Long power plant through 49 percent equity investment in An Binh Energy and Infrastructure Fund (ABEIF), a fund dedicated for investment in energy and infrastructure projects in Vietnam in July 2020.
Management of power purchase agreements
Of total electric power generted by RATCH’s power plants, over 87 percent was sold to Electricity Generating Authority of Thailand. As such, the management of the power purchase agreements with EGAT is significant to the Company’s revenue management.
RATCH Group PCL.
Sustainability Report 2020
77
 Power plant
Type
 Equity installed capacity (MW)
  Electric power distributed under PPAs (MWh)
Electric power distributed in National Electricity Market (MWh)
 Kemerton
 Open cycle gas Turbine
 308
 94,252
 -
 BP Kwinana
 Cogeneration
 35.4
 797,000
 -
 Townsville
 Combined cycle
 234
 212,922
 -
 Starfish Hill
 Wind power
 33
 89,803
 -
 Mount Emerald
  Wind power
  180.45
  349,673
  -
 Collinsville
 Solar power
 42.5
 86,078
 -
 Kemerton (Black Start)
Diesel engine
7.2
-
-
 Windy Hill
 Wind power
 12
 -
 24,491
 Toora
  Wind power
  21
  -
  51,750
 Yandin*
 Wind power
 149.94
 236,057
  Collector*
 Wind power
 226.8
 8,899
    Note : The under-construction Yandin and Collector Wind Farms are underway of Grid Compliance Test prior to commercial operation.
   Availability Payment (AP)
• Electric power at demanded voltage generated at the quality (or specifications) specified in contracts
• Electric power specified in contracts
RATCH’s revenue under PPAs
Energy Payment (EP)
Cost of energy
ordered to use
in power generation
   