Construction management for timely product delivery
To ensure that under-construction projects meet power purchase regulations, generating companies must make down payment. In case that power plant misses the scheduled commercial operation date, the generating companies must forgo the down payment and shoulder damage claims or other payments.
RATCH tasks the Project Development Function to ensure the engineering and construction of under-construction projects strictly meet schedules, budgets, contractual conditions and relevant laws. At present, 7 power plant projects in Thailand and overseas are under construction with 1,326.11 MW in equity installed capacity. Aside, two electric train projects are under construction.
Power plant project
  Location
 Project
Equity installed capacity (MW)
Scheduled commercial operations
Customer/ stakeholder
Thailand
 RATCH Cogeneration (Extension)
 29.99
 2022
 Industrial customers
 Hin Kong Combined Cycle Power Plant
 714
 2025
 EGAT
 Nexif RATCH Energy Rayong Power Plant
  45.08
  2022
  EGAT
  Australia
Yandin Wind Farm
149.94
2021
Industrial customers
 Collector Wind Farm
 226.8
 2021
 Industrial customers
 Indonesia
  Riau Combined Cycle Power Plant
  145.15
  2021
  Perusahaan Listrik Negara
 Vietnam
 Ecowin Wind Farm
 15.15
 2021
 Vietnam Electricity
   Infrastructure
Communications and customer engagement
RATCH’s power plants hold meetings to hear customers’ complaints and suggestions, to understand their needs and find mutual solutions so that the operations meet customer expectations.
 Location
 Project
Shareholding (%)
 Scheduled operation date
Customer/ stakeholder
Thailand
  Monorail Pink Line
 10
  2022
  Commuter/MRT
 Monorial Yellow Line
 2022
 Commuter/MRT
  