Company News
23 Apr 2015
Hongsa Power Plant reaches 90% completion of efficiency test, generated electricity helped securing national grid during Myanmar natural gas field shutdown Its COD schedules in upcoming June
Share to :

Nonthaburi - Ratchaburi Electricity Generating Holding Public Company Limited (RATCH) reported that 626-MW Hongsa thermal power plant unit 1 operated by Hongsa Power Company Limited (HPC) has completed over 90% of performance efficiency test specified by the power purchase agreement (PPA). Its commercial operation will be commenced on 2 June 2015 as scheduled.

The Hongsa power plant unit 1 has started synchronization of its generation to the power grid of Electricity Generating Authority of Thailand (EGAT) since 28 February and performed efficiency test according to PPA's requirement since mid-March.  In the event of Myanmar natural gas field shutdown during 10-19 April, Hongsa unit 1 has continued the test process and its average generation since 12 April has been operated around 450 MW. Electricity supplied by the plant helped Thailand power system fully serving domestic power demand in that critical period. From 12 to 21 April 2015, Hongsa unit 1 generated around 85 million units of electricity supporting reduction of 20 million-litre fuel oil approximately in electricity generating.          

Mr. Pongdith Potchana, Chief Executive Officer of RATCH, said that the 1,878-MW Lignite-fired Hongsa thermal power plant was regarded as a large power base load that can enhance the national power stability and maintain the electricity tariff at acceptable level. It also appeared that the plant helped supply electricity for peak demand on 7 and 21 April 2015 effectively. The company is strongly confident that the performance efficiency of Hongsa power plant unit 1 will certainly meet the EGAT’s criteria and international standards and will be able to start commercial operation on 2 June 2015 as planned. Meanwhile, the efficiency test of Hongsa power plant unit 2 and 3 are expected to finish as scheduled in PPA and their commercial operations will commence on November 2015 and March 2016 respectively.   

Hongsa lignite mine-mouth thermal power plant is a joint project under operation of Hongsa Power Company Limited where RATCH, Banpu Public Company Limited and Lao Holding State Enterprise co-owned its equity stake of 40%-40%-20% respectively. Regarded as the first and largest lignite-fired power plant in Lao PDR, this 1,878-MW power plant located in Sayaboury Province, comprises of 3 units with 626 MW capacity each.

Share to :
Back
Latest Activities
Company News
RATCH Group Successfully Issues THB 3.5 Billion Green Debentures to Enhance Renewable Portfolio Efficiency and Advance Net Zero Ambitions
Nonthaburi – RATCH Group Public Company Limited has succeeded the issuance of Unsubordinated and Unsecured Green Debentures with a tenor of 4 years and a fixed interest rate of 1.94% per annum, totaling THB 3,500 million.
10 Apr 2026
Company News
NNEG เริ่มเดินเครื่องส่วนขยาย 28.75 MW ตอบสนองความต้องการและความมั่นคงด้านพลังงานแก่ภาคอุตสาหกรรม
บริษัท ผลิตไฟฟ้า นวนคร จำกัด (NNEG) จัดพิธีเปิดการผลิตไฟฟ้าส่วนขยาย มูลค่าโครงการประมาณ 1,724 ล้านบาท โดยติดตั้งเครื่องยนต์ก๊าซ (Gas Engine) พร้อมอุปกรณ์อื่นที่เกี่ยวข้อง กำลังการผลิตไฟฟ้าสุทธิ 28.75 เมกะวัตต์ และความสามารถผลิตไอน้ำ 8 ตันต่อชั่วโมง
01 Apr 2026
Company News
RATCH Posts THB 6,220 Million Net Profit in 2025; Approves THB 3,480 Million Dividend, THB 1.60 per share, Payable on 22 May 2026
Nonthaburi – RATCH Group Public Company Limited reported net profit of THB 6,220 million for its operating performance in 2025 and the Earnings before interest, taxes, depreciation, and amortization (EBITDA) of THB 15,322 million.
27 Feb 2026